Questions and discussion about using ProcessMaker: user interface, running cases & functionality
By heemalkumar
#826071
Hi All
I am doing a process, where i have 3 tasks allocated to 3 departments. Once each department completes the case in those 3 tasks, then I want the case to come to my Team - condition is all 3 to complete case, then only it comes to my team.

I have set a variable equal to 0, and I have put a trigger to fire so that when each department completes their case, the variable count increases by 1. So how will i do this, that when my variable is equal to 3, that case comes to my team?

I hope i have explained it well?
User avatar
By amosbatto
#826092
Why don't you create a process like this one?
parallelTasksFor3Departments.png
parallelTasksFor3Departments.png (23.11 KiB) Viewed 4329 times
That way you know that the three departments have completed their tasks before it gets to your team.

Are you looking for a more intelligent approach to[…]

The 1Win Clone Script is a pre-built solution that[…]

Aviator Clone Script replicates the renowned Aviat[…]

From converting physical assets into digital asset[…]