#782727
I am using PM2.5.4, as the process administrator.

when there are parallel tasks in the "review", the columns "task" and "current user" just display the same name.
but actually there are different task names and users.
e.g: in one process, there are 3 parallel tasks, names: TASK1, TASK2, TASK3, when process comes to the parallel task,
there are 3 lines in "review", but the displayed task name and current user are same. only TASK1.
Attachments
error_display.JPG
error display
error_display.JPG (55.03 KiB) Viewed 3317 times