Hi everyone.

Currently I'm using Processmaker ver 3.2.

I'm having an error after updating the date data in a grid table.
The user select today's date in the grid table then submit the dynaform.
When the user want to open the case to update another field, the error shows the initial date that the user chosen are backdated as per picture below.
This error doesn't happened regularly, only once in a while.
image002.jpg
Grid Error
image002.jpg (112.21 KiB) Viewed 888 times
I have already maximize all the perimeter in the php.ini
Is there any other way to tackle this issue.

Thank you in advance.

Regards,
Ikhwan Afiq