Dear Processmaker community,
I have an output document that displays a grid of various activities. The grid contains date fields.
The date fields are set to the format DD-MM-YYYY when used in dynaforms and work great.
However in output documents these are shown as YYYY-MM-DD hh:mm:ss which I cant have showing in various contracts
I understand that i could use a trigger to set the format of date variables before I generate the contract - but i only know how to do this for single variables, and not within a grid.
In short, I need grid dates to show as DD/MM/YYYY in output documents.
Is there a simple solution to this?
I've also tried adding javascript but this doesn't seem to get executed before HTML2PDF.
I've attached photo example.
Many thanks!
Daniel
I have an output document that displays a grid of various activities. The grid contains date fields.
The date fields are set to the format DD-MM-YYYY when used in dynaforms and work great.
However in output documents these are shown as YYYY-MM-DD hh:mm:ss which I cant have showing in various contracts
I understand that i could use a trigger to set the format of date variables before I generate the contract - but i only know how to do this for single variables, and not within a grid.
In short, I need grid dates to show as DD/MM/YYYY in output documents.
Is there a simple solution to this?
I've also tried adding javascript but this doesn't seem to get executed before HTML2PDF.
I've attached photo example.