- Wed Nov 08, 2017 12:18 pm
#796080
Hello eveyone,
I have 2 servers, one production server and one develop server that contains the ProcessMaker 3.0.1.8-community.
In those servers, I have created the same process "Test".
The process looks like the following:
So in production server, I have created 4 cases in the process "Test". 2 cases are in Task 1 and the other 2 cases are in Task 2.
Now in develop server, I change completely the process like:
And finally, I want to export the process "Test" of the develop server and import it to the production server.
What will happen with the TO_DO cases if I import to the process Test of the production server ?
Thanks
Best Regards,
I have 2 servers, one production server and one develop server that contains the ProcessMaker 3.0.1.8-community.
In those servers, I have created the same process "Test".
The process looks like the following:
So in production server, I have created 4 cases in the process "Test". 2 cases are in Task 1 and the other 2 cases are in Task 2.
Now in develop server, I change completely the process like:
And finally, I want to export the process "Test" of the develop server and import it to the production server.
What will happen with the TO_DO cases if I import to the process Test of the production server ?
Thanks
Best Regards,
Attachments
ProcessTestNEW.PNG (17.47 KiB) Viewed 2394 times
ProcessTestOLD.PNG (14.34 KiB) Viewed 2394 times